As of 30 September 2026

Where grid connection becomes Germany's bottleneck

How fast data centres get built depends on the connection capacity available at a specific point on a specific network, by a specific date. This map shows where that limit runs: what is in operation, what is planned and where a site could still realistically be secured.

How to read the counts. The built layer shows city clusters rather than individual buildings: one circle per market. A circle is sized by published IT capacity in megawatts where a figure exists, and drawn as a small fixed mark where none does. Sources disagree on the national total, and we have not averaged them. Cloudscene counts 529 data centres in Germany; a colocation-portfolio database counts 194 existing and 43 upcoming; trade coverage says roughly 500. The gap comes from scope: every facility including small hosting, against colocation only. Live IT load is shown where a figure is published, which is Frankfurt, Munich and Berlin.

How to read the dots. The dots are not our projects. They mark positions in the market, graded by how settled the information is. Built and planned come from the evidence base and carry its tier. Potential is our own inference from ownership and existing grid connections. It is deliberately the thinnest layer on the map: nobody publishes this information, and it can be gathered only in conversations on the ground, never at a desk.

Siting drivers from our siting model (areas approximate; off by default):
Where each customer is headquartered, relative to the data centre it uses (added 8 September 2026; the data centres come from our research, the headquarters from public information outside it):
Frankfurt / Rhine-Main Dummerstorf (Schwarz Digits) Wustermark (Virtus) Lübbenau (Schwarz Digits) Berlin Munich Hamburg Düsseldorf Stuttgart Bergheim (Microsoft) Dietzenbach (Google) AWS European Sovereign Cloud Nauen (maincubes) Großkrotzenburg (Uniper) Grevenbroich (Microsoft) Eisenach (developer FAB, project stalled) Weisweiler (RWE land)
Built Planned Potential (our inference) Circle area follows published IT capacity in MW (Frankfurt is capped to fit the map). A position with no published figure is a small fixed mark, so most planned and all potential positions are not sized.
Favourable (solid fill) Constrained (dashed outline, light fill) Unfavourable (hatched) Each driver keeps its own colour. The rating is carried by the fill, never by colour alone. Click a shaded area for its rating, evidence and source.

What the map does not show

We name these gaps explicitly, because the next piece of work lies in them.

Why the control zones matter

Since 1 April 2026 the four transmission system operators have allocated extra-high-voltage connection capacity through the maturity procedure (Reifegradverfahren) instead of first come, first served. Applications are collected in fixed rounds per control zone and ranked together. A site therefore competes for a switching bay with the other applicants in its own zone. A site 30 kilometres away, across a zone boundary, is in a different contest. That is why Nierstein and Hanau are neighbours only on the map.

The zone shading is approximate. Each Land is coloured by its predominant transmission operator. The real control-zone boundaries do not follow Land borders, and Hesse, Bavaria and North Rhine-Westphalia are split in ways this shading does not show.

A site below the transmission level can still be caught by the procedure. Added 9 September 2026. The maturity procedure covers connections to the transmission grid, the extra-high-voltage level of 220 and 380 kV. A load of roughly 5 to 10 MW and more connects at 110 kV, which in Germany is the high-voltage level of the distribution grid; a load of roughly 100 MW connects at 380 kV. A site of 20 to 50 MW therefore sits at distribution level and looks exempt. It usually is not: TransnetBW's own procedure page lists ad-hoc requests from distribution operators to the transmission grid as covered too. Where the local distribution operator has no headroom, it must apply upstream. The site then sits in the queue as one line in someone else's application, without the levers (secured land, permits, equipment orders) that directly improve a ranking in the procedure. Several planned sites on this map, among them Colt DCS at 54 MW and Data Center Partners' Munich site at 17 MW, fall exactly into this size band.

Where each siting driver is strongest and weakest

Our driver model weighs the five factors that do most to decide where a data centre goes in Germany. Four of the five are now asked for explicitly in a connection application under the maturity procedure. Each driver has its own toggle above the map, off by default. Switching one on shades the areas the model rates for that driver: solid fill where the evidence rates it favourable, a dashed outline with light fill where it is constrained, and hatching where it is unfavourable or absent. Click a shaded area for its rating, the statement it rests on and the source.

What this layer is not. These are the three or four areas the driver model actually analysed, drawn as ellipses that approximate their extent. They are not a national survey. A blank area under any of the five toggles means the model has not assessed it, and says nothing about the driver there. The ratings are this project's own synthesis (labelled [inference] in the source document) and rest on evidence of only medium confidence. Berlin's growth rate comes from a trade source not checked against a primary. The Berlin allocation figure comes from the operator's own results as reported by ZfK (May 2026), and the Nauen status was checked against independent sources on 21 September 2026.

Appendix: every position on the map

Sorted by status, then size. Nothing here is verified beyond the tier stated.

PositionStatusScalePartyControl zoneSource, tier, confidence
Frankfurt / Rhine-Main
Hesse
built 131 facilities
997 MW
131 facilities listed on Cloudscene. Equinix, Digital Realty (24 data centres in the metro, per its own page), NTT, CyrusOne, Vantage, CloudHQ (Offenbach campus, 112 MW critical IT load), Telehouse, NorthC and others TenneT JLL (2026-04-17; mid-year 2026); Bitkom (2026-03); Mainova via t3n (2026-03-18); TenneT (n.d., MainNetzausbau); Mainova (n.d.); Amprion (2021); Cloudscene (2026); Digital Realty (n.d.); CloudHQ (n.d.)
Tier 1-2 (grid operators, city utility) for the connection constraint; Tier 3-4 (Bitkom, JLL, Cloudscene) for capacity and counts · High on the connection constraint and the order of magnitude; medium on exact MW, which differ by definition between JLL (colocation and hyperscale) and Bitkom (all data centres) · checked 2026-09-30
Munich
Bavaria
built 55 facilities
102 MW
55 facilities listed on Cloudscene. NorthC (two sites: Balanstrasse, 2 MW; Wamslerstraße, 1.17 MW, taken over from Colt on 1 September 2025), Equinix and others TenneT Cloudscene (2026); JLL (2026-04-17); NorthC (n.d.; 2025); Data Center Knowledge (2026-03-18)
Tier 4 (directory, broker) + Tier 5 (operator) · Medium · checked 2026-09-30
Hamburg
Hamburg
built 53 facilities 53 facilities listed on Cloudscene. NorthC (Süderstraße 198: 1.17 MW today, 4.1 MW installed electrical power listed as a future upgrade), NTT and others 50Hertz Cloudscene (2026); NorthC (n.d.; 2025); Data Center Knowledge (2026-03-18)
Tier 4 (directory) + Tier 5 (operator) · Medium · checked 2026-09-30
Berlin
Berlin
built 45 facilities
136 MW
45 facilities listed on Cloudscene. NorthC (Gradestraße 60, taken over from Colt on 1 September 2025), Google cloud region and others 50Hertz ZfK (2026-05-04); JLL (2026-04-17); Cloudscene (2026); NorthC (n.d.)
Tier 3 to 4 · Medium to high · checked 2026-09-30
Düsseldorf
North Rhine-Westphalia
built 38 facilities 38 facilities listed on Cloudscene. Digital Realty (three data centres on In der Steele, 16,750 m² colocation space in total), Equinix, NorthC (In der Steele 37A, taken over from Colt on 1 September 2025), NMMN (sells colocation in a facility it describes as over 10,000 m² and 20 MW), aixit Amprion Cloudscene (2026); JLL (2026-04-17); Digital Realty (n.d.); NorthC (n.d.); NMMN (n.d.)
Tier 4 to 5 · Medium · checked 2026-09-30
Nuremberg
Bavaria
built 27 facilities 27 facilities listed on Cloudscene. NorthC (Am Tower 5), noris network and others TenneT Cloudscene (2026); NorthC (n.d.)
Tier 4 · Medium · checked 2026-09-30
Stuttgart
Baden-Württemberg
built 25 facilities 25 facilities listed on Cloudscene. NMMN (three sites: Gropiusplatz, Schickardstraße, Neue Brücke), nexspace (new Sternhöhe site, opening given as 09/2026 on its English page and Q4 2026 on its German page) TransnetBW Cloudscene (2026); NMMN (n.d.); nexspace (n.d.)
Tier 4 to 5 · Low to medium · checked 2026-09-30
Cologne
North Rhine-Westphalia
built 15 facilities 15 facilities Amprion Cloudscene (2026)
Tier 4 · Low to medium · checked 2026-09-30
Dortmund
North Rhine-Westphalia
built 9 facilities 9 facilities Amprion Cloudscene (2026)
Tier 4 · Low · checked 2026-09-30
Hanover
Lower Saxony
built 9 facilities 9 facilities TenneT Cloudscene (2026)
Tier 4 · Low · checked 2026-09-30
Bremen
Bremen
built 8 facilities 8 facilities listed on Cloudscene, including ColocationIX TenneT Cloudscene (2026)
Tier 4 · Low · checked 2026-09-30
Leipzig
Saxony
built 7 facilities 7 facilities 50Hertz Cloudscene (2026)
Tier 4 · Low · checked 2026-09-30
Karlsruhe
Baden-Württemberg
built 7 facilities 7 facilities TransnetBW Cloudscene (2026)
Tier 4 · Low · checked 2026-09-30
Dresden
Saxony
built 5 facilities 5 facilities 50Hertz Cloudscene (2026)
Tier 4 · Low · checked 2026-09-30
Kiel
Schleswig-Holstein
built 3 facilities 3 facilities TenneT Cloudscene (2026)
Tier 4 · Low · checked 2026-09-30
Bielefeld
North Rhine-Westphalia
built 2 facilities 2 facilities TenneT Cloudscene (2026)
Tier 4 · Low · checked 2026-09-30
Hanau (Google)
Hesse
built not published Google TenneT Stadt Hanau (2026-04-28); Hessische Landesregierung (2026-04-28); Google (n.d.); Data Center Knowledge (2026-03-18)
Tier 2 (city, state) + Tier 5 (operator) · High · checked 2026-09-30
Nierstein
Rhineland-Palatinate
planned 482 MW NTT Global Data Centers Amprion heise online / dpa (2026-01/02), citing NTT
Tier 3 (independent press, company statement) · High on operator, size and zoning; medium on timing · checked 2026-09-30
Dummerstorf (Schwarz Digits)
Mecklenburg-Vorpommern
planned 240 MW Schwarz Digits 50Hertz Schwarz Gruppe press release (2026-08-27); ZDFheute / dpa (2026-08-27); heise online (2026-08-27)
Primary (company) + Tier 3 · High on the announcement; low on timing, which is permit-dependent · checked 2026-09-30
Wustermark (Virtus)
Brandenburg
planned 204 MW Virtus (ST Telemedia) 50Hertz Virtus Wustermark campus page (accessed 2026-09-30); STT GDC / Virtus newsroom (2023-09-04)
Primary (company) · High on the company's current figures; timing has slipped once · checked 2026-09-30
Lübbenau (Schwarz Digits)
Brandenburg
planned 200 MW Schwarz Digits 50Hertz Schwarz Digits release (2025-11-17, via Silicon Saxony reprint) and Datacenter Lübbenau page; Stadt Lübbenau/Spreewald (2025-11)
Primary (company) + Tier 2 (municipality) · High · checked 2026-09-30
East of Berlin (Colt DCS)
Brandenburg
planned 54 MW Colt DCS 50Hertz Colt DCS press release (2025-04) and Berlin 1 and 2 location page; CIO.de / dpa (2025-07)
Primary (company) + Tier 3 · High on the plan; medium on timing · checked 2026-09-30
Munich (Data Center Partners)
Bavaria (Unterschleißheim, north of Munich)
planned 17 MW Data Center Partners TenneT DatacenterDynamics (2025); CMS Hasche Sigle on the EnEfG cabinet draft (2026)
Tier 3 · Medium: single trade source for the project · checked 2026-09-30
Bergheim (Microsoft)
North Rhine-Westphalia
planned not published Microsoft Amprion Land NRW (2026-03-12); Microsoft (2026-03-12; 2024-02-15)
Tier 2 (state) + Tier 3 · High on the event, medium on the €3.2bn split · checked 2026-09-30
Bedburg (Microsoft)
North Rhine-Westphalia
planned not published Microsoft Amprion Microsoft (2026-03-12) press release; heise online (2026-07-01)
Primary (company) + Tier 3 · High on permit and status; MW unknown · checked 2026-09-30
Elsdorf (Microsoft)
North Rhine-Westphalia
planned not published Microsoft Amprion Microsoft (2026-03-12) press release; heise online (2026-07-01)
Primary (company) + Tier 3 · Medium: permit status dated July 2026 · checked 2026-09-30
Dietzenbach (Google)
Hesse
planned not published Google TenneT Google Cloud press release (2025-11-11); Kreisstadt Dietzenbach (2025-11)
Primary (company) + Tier 2 (municipality) · High on the announcement and the heat deal; MW not published · checked 2026-09-30
AWS European Sovereign Cloud
Brandenburg (exact site not published)
planned not published AWS 50Hertz AWS press releases: press.aboutamazon.com (2026-01-15), aboutamazon.eu (2024-05-15), aboutamazon.de (2024-06-19)
Primary (company) · High on the commitments; low on the exact site · checked 2026-09-30
Nauen (maincubes)
Brandenburg
planned not published maincubes 50Hertz maincubes website and press releases (2024 to 2026, captured 2026-09-25); Stadt Nauen; connect-professional; datacenter-insider.de
Tier 5 company primary, corroborated by the municipality and two trade outlets · High on status; medium on dates, which the company states inconsistently · checked 2026-09-30
Großkrotzenburg (Uniper)
Hesse
planned not published Uniper TenneT Uniper / TenneT joint release (2026-01-22, via MarketScreener reprint); IZ Immobilien Zeitung (2026-07); ms-aktuell (2026-09-06)
Primary (via reprint) + Tier 3 · High on the transaction; medium on the data-centre area · checked 2026-09-30
Grevenbroich (Microsoft)
North Rhine-Westphalia
planned not published Microsoft Amprion Microsoft (2026-07-01) press release; Stadt Grevenbroich news and project page (2026-07); heise online (2026-07-01); Handelsblatt (2026); datacenter-insider.de (2026-07); Landtag NRW petition committee (2025-01-14)
Primary (company) + Tier 2 (city) + Tier 3 · High on the announcement and site; low on investment size; medium on consent · checked 2026-09-30
Eisenach (developer FAB, project stalled)
Thuringia
planned not published FAB, Leipzig (developer; end investor not yet named) 50Hertz Eisenach Online (July 2026, report of the council session of 1 July); Stadt Eisenach, Blue Future project page; Rhönkanal (2026-03)
Tier 2 (city) + Tier 3 · High on the vote, date and outcome; medium on the pre-vote plan figures · checked 2026-09-30
Frimmersdorf (RWE land)
North Rhine-Westphalia
planned not published RWE (site owner) Amprion Stadt Grevenbroich (plan presentation with NRW, Rhein-Kreis Neuss and RWE); NRW.URBAN project page (accessed 2026-09-30); Stadt Grevenbroich Microsoft Q&A (2026-07)
Tier 2 (city, state development company) · Medium to high on the plan; timing depends on the investor tender · checked 2026-09-30
Weisweiler (RWE land)
North Rhine-Westphalia
potential not published RWE (site owner) Amprion RWE 'energised Land' page (accessed 2026-09-30); Reuters (2026-08-13); KVBG Anlage 2
Tier 5 + Tier 1 (statute) + inference · Low · checked 2026-09-30
Neurath (RWE land)
North Rhine-Westphalia
potential not published RWE (site owner) Amprion KVBG Anlage 2; Stadt Grevenbroich project page (2026-07); RWE 'energised Land' page
Tier 1 (statute) + Tier 2 (city) + Tier 5 + inference · Low · checked 2026-09-30
Hürth (RWE land)
North Rhine-Westphalia
potential not published RWE (site owner) Amprion RWE Knapsacker Hügel site page (accessed 2026-09-30); RWE 'energised Land' page
Tier 5 + inference · Low · checked 2026-09-30
Niederaussem (RWE)
North Rhine-Westphalia
potential not published RWE Amprion RWE AG press release (2011-09-23, via firmenpresse); CIO.de (c. 2016-17); KVBG Anlage 2
Primary (company, 2011) + Tier 3 + Tier 1 (statute) · High on the history; low on any future use · checked 2026-09-30

Sources

AWS. (2026, January 15). AWS launches AWS European Sovereign Cloud and announces expansion across Europe [Press release]. Primary.

CBRE. (2025). Frankfurt becomes a 1GW data centre market; 2025 Global Data Center Investor Intentions Survey.

Cloudscene. (2026). Germany data center market overview. Directory; self-reported, tier 4.

Digital Realty. (n.d.). EMEA data centers. Company site; primary for its own facilities.

Google. (2026). 5,5 Milliarden Euro für Deutschlands digitale Zukunft; hessenschau (2026); Hessen state government. Dietzenbach and Hanau.

Land Nordrhein-Westfalen. (2026, March 12). Spatenstich für die Microsoft Rechenzentren im Rheinischen Revier. State government; tier 2. With Microsoft (2026) and Handelsblatt (2026) for the €3.2bn figure.

NorthC. (n.d.). Data centre locations. Company site; primary for its own facilities.

Data Center Dynamics. (2026). German utility RWE completes Niederaussem data center.

Data Center Knowledge. (2026). Germany's data center market expands amid power and regulatory pressures.

RWE. (n.d.). "energised Land" — Energy for data centres. Company marketing page; tier 5 and interested on every figure.

TechPolicy.Press. (2025). Germany's data center boom is pushing the power grid to its limits.

Übertragungsnetzbetreiber (50Hertz, Amprion, TenneT Germany, TransnetBW). (2026, February 5). Reifegradverfahren für Netzanschlüsse an das Übertragungsnetz (V1.00), and the joint press release of the same date. Primary.

Uniper & TenneT Germany. (2026, January 22). Reaching the goal faster together. Primary, read in a reprint.

Internal: our Germany profile and risk register; our research on customers, demand and hurdles; and our siting model (the five siting-driver layers).


Map 2 · exploratory · outside the evidence base

Educated guesses: where nobody has moved in yet

Map 1 shows only what this project has evidence for. This second map works the other way round. Using the same five drivers, it asks where in Germany the conditions that made the Rhenish belt attractive for data centres might also exist, in areas where, as far as our research has found, no developer, utility or hyperscaler has moved in yet. Every rating here is our own reasoning from public knowledge of Germany's coal exit and grid build-out, done at Moritz's request. None of it has been checked against a primary source, and none of it carries a project citation as Map 1 does. Read it as a list of places worth a site visit, not as a finding.

Why these five areas. Two are Germany's other two federally designated lignite regions (the Rhenish belt, already on Map 1, is the third): Lusatia, where LEAG plays the role RWE plays in the Rhenish belt, and the Mitteldeutsches Revier south of Leipzig, where MIBRAG does. The third, the wider Ruhr, extends the logic of existing power-plant connections to the hard-coal and gas fleet beyond the Rhenish core, in the same crowded Amprion zone as the committed Microsoft cluster. The fourth, the Schleswig-Holstein wind corridor, works by a different mechanism: new transmission capacity is being built there, SuedLink to carry wind power south and NordLink to link with Norway, and no industrial connection is inherited. The fifth, added 8 September 2026, is different again: Rhein-Neckar & Neckarsulm was chosen for its customers, because two named, well-funded buyers (SAP, Schwarz Digits) already sit there, according to our demand research. The "Potential customers" layer below shows that link. The faint grey dots are Map 1's built and planned positions, shown for orientation only; they are not part of this layer.

Same five drivers, same colours, off by default:
Who might buy: five hypotheses, each checked against its sources on 30 September 2026, with the basis, tier and sources on click. Two rest on published computing capacity of their own (Jülich, BWI), two on a federal cloud contract won as suppliers (SAP, Schwarz Digits), and one on a large power user with a new substation (BASF Schwarzheide). None is a tenant, and none matches the tenant classes in our customer research:
Favourable (solid fill) Constrained (dashed outline, light fill) Unfavourable or unknown (hatched) Click a shaded area for the reasoning and its (unverified) basis.

Sources for Map 2 (general knowledge, not project research): Bundesministerium für Wirtschaft und Klimaschutz / Strukturstärkungsgesetz Kohleregionen (2020), for the three designated German lignite regions and their structural funding. LEAG, public statements on converting former mining and plant sites ("GigawattFactory"). TenneT / 50Hertz / Amprion, public project information on the SuedLink and NordLink corridors; their roles were checked against TenneT's SuedLink page on 30 September 2026. Schleswig-Holstein state government, public statements of its hydrogen and power-to-X strategy. Apart from that one check, none of these has been compared with a primary source. Every figure and claim above needs verification before it is used for anything beyond choosing where to look next.


Map 3 · political and municipal investment climate

Where local politics says yes, and where it has already said no

Driver 3 on Map 1 rates consent and local politics by region. This map asks the same question where it is actually decided: one council, one mayor, one vote. Every marker below is a named, dated event or decision. That includes the unfavourable ones, which we found by deliberately searching for opposition, as our research standard requires: it tells us to look actively for evidence against our own view.

How to read this map. A favourable marker is active support from an elected mayor or council. For Monheim am Rhein it marks a fiscal-policy benchmark of how far investment-friendliness goes nationally; the town has no known data-centre interest and is on the map for comparison only. An unfavourable marker is a recorded council vote against, or an operator halting work after protest. Contested sits between the two: a citizen initiative and an elected council at odds, with the outcome still open.

Added 9 September 2026, off by default: five large, resource-intensive projects in other sectors (semiconductors, batteries, electric vehicles, grid transmission), with the same three-way political rating, drawn as a diamond so they are never mistaken for data-centre cases:
Grevenbroich · contested Eisenach · unfavourable Monheim am Rhein (national benchmark, no data-centre interest known) · favourable Groß-Gerau · unfavourable Maintal · unfavourable Birstein · favourable
Favourable Contested Unfavourable Click a marker for the event, its date and its source.
Comparable project (other sector): a diamond, coloured the same three ways

Who is paying: public and private capital compared

Added 9 September 2026. The chart shows every disclosed funding figure for the six sites on this map, together with the German academic and research-computing funding gathered in the same session (our demand research, segment 8), summed and compared. Only stated, disclosed figures are charted. Nobody involved has disclosed the investment for Grevenbroich or Birstein. Trade press floats ranges, but turning a range into a point estimate would present a guess as a fact, so both are left out here and marked undisclosed in their own panels.

Dresden-Klotzsche (ESMC/TSMC, semiconductors) · €10,000m (mixed). About €10bn in total (ComputerBase, 2024-08-20), with €5bn German state aid approved by the European Commission on 20 August 2024 under the EU Chips Act principles (European Commission, 2024). ESMC is a joint venture of TSMC with Bosch, Infineon and NXP. Comparable-project layer, added 2026-09-09.Dresden-Klotzsche (ESMC/TSMC, semiconductors)€10,000m SuedLink corridor (grid transmission) · €10,000m (regulated). About €10bn, invested by TenneT and TransnetBW and depreciated over 40 years through regulated network charges paid by electricity users (TransnetBW; Wissenschaftliche Dienste des Bundestages, 2024). Not risk equity, not a budget subsidy. Comparable-project layer, added 2026-09-09.SuedLink corridor (grid transmission)€10,000m Magdeburg (Intel, cancelled) · €9,900m (public). €9.9bn federal subsidy pledged in 2023 and never paid out; Intel paused the project in September 2024 and abandoned it in July 2025 for its own financial reasons (Table.Briefings, 2025-07-26; ZDFheute, 2025). Comparable-project layer, added 2026-09-09.Magdeburg (Intel, cancelled)€9,900m Groß-Gerau (Vantage, rejected) · €2,500m (private). About €2.5bn per hessenschau (2026-02); the city's own release gives 174 MW on 14 ha and the 14 to 18 vote of 3 February 2026 but no investment figure (Kreisstadt Groß-Gerau, 2026). Proposed, not deployed, capital.Groß-Gerau (Vantage, rejected)€2,500m Grünheide (Tesla battery-cell plant) · €1,100m (private). About €1.1bn, raised from €900m, for battery-cell production at Grünheide from 2027 with 1,500 new jobs (Elektroauto-News, 2026). This is separate from the contested 2024 expansion of vehicle capacity. Comparable-project layer, added 2026-09-09.Grünheide (Tesla battery-cell plant)€1,100m Eisenach (FAB, stopped) · €1,000m (private). Roughly €1bn planned investment volume, per datacenter-insider (2026-07), for developer FAB's plan to develop and sell on. Stopped for now by the council's 19 to 16 vote of 1 July 2026; proposed, not deployed, capital.Eisenach (FAB, stopped)€1,000m Maintal (EdgeConneX, paused) · €1,000m (private). Roughly €1bn, 'dem Vernehmen nach' (reportedly) per hessenschau (2026-05), not a figure EdgeConneX published. The project is on hold after protest against its planned on-site gas plant; EdgeConneX is looking at other power concepts. Proposed, not deployed, capital.Maintal (EdgeConneX, paused)€1,000m Heide (Northvolt Drei; parent insolvent) · €902m (public). €902m approved by the European Commission in January 2024: a €700m direct grant (about €564m federal, €136m Schleswig-Holstein) and a €202m guarantee (Battery-News, 2024-01-09). Northvolt went insolvent; in April 2026 the Heide project company received a first partial construction permit and repaid €153m of a convertible bond to the federal and state governments (ecomento, 2026-04-13). Comparable-project layer, added 2026-09-09.Heide (Northvolt Drei; parent insolvent)€902m JUPITER exascale system, Jülich · €500m (public). €500m for system and operations over about six years: €250m EuroHPC JU, €125m each from BMFTR (formerly BMBF) and Land NRW (BMFTR, 2025; Forschungszentrum Jülich via idw).JUPITER exascale system, Jülich€500m RWTH Aachen AI-Center building · €180m (public). Up to €180m from the NRW-Plan for a new computer-science building with an integrated AI Center (MKW NRW, 2026-03-26).RWTH Aachen AI-Center building€180m Fraunhofer NG-HPDAC, Bonn · €56.0m (public). €56m for construction and initial equipment, including a data centre of about 800 m² (Fraunhofer IZB, 2026-06-08).Fraunhofer NG-HPDAC, Bonn€56.0m DKRZ HLRE-4 'Levante', Hamburg (2022) · €45.0m (public). €45m for the HLRE-4 system 'Levante', in operation since March 2022, under the 2017 financing agreement: 45% Helmholtz, 40% Max Planck, 15% Free and Hanseatic City of Hamburg, with renewal about every five years (Hereon, 2017; DKRZ, 2022). A successor (HLRE-5) was being prepared; its funding was not found.DKRZ HLRE-4 'Levante', Hamburg (2022)€45.0m NHR-Verbund AI-capacity tranche, 2026-2030 · €30.7m (public). Up to €30.7m, 2026 to 2030, from the federal special fund for infrastructure and climate neutrality, for AI-capable high-performance computing at universities, on top of the NHR's standing funding of up to €62.5m a year, continued for 2027 (GWK decision of 10 July, as reprinted).NHR-Verbund AI-capacity tranche, 2026-2030€30.7m KIT Karlsruhe AI data centre · €24.0m (public). About €24m, federal and Baden-Württemberg funding, for a new AI and scientific-computing data centre of about 2 MW, expandable to 10 MW, to be finished by the end of 2029 (KIT, 2026).KIT Karlsruhe AI data centre€24.0m
Private commercial Public (academic or research, or a subsidy) Mixed (private and public in one project) Regulated utility (funded through consumers' network charges; neither risk equity nor subsidy)

Totals: all 14 disclosed figures on this page, €37,238m combined. Private commercial: €5,600m across four projects (the three Map 3 data-centre cases plus the Grünheide expansion). Three of the four, Groß-Gerau, Eisenach and Maintal, are now rejected, paused or stopped, so this is capital proposed rather than deployed. Public: €11,637.7m across eight items: six academic and research programmes (segment 8) plus two subsidy pledges to private projects that have since failed (Magdeburg, Heide). That deserves attention: most of the disclosed "public" figure on this page is subsidy committed to industry rather than spending on public research infrastructure. Mixed: €10,000m, one project (Dresden/ESMC), roughly half private capital and half federal subsidy in the same fab. Regulated: €10,000m, one project (SuedLink), paid for by the grid operators and recovered from every electricity consumer through network charges; it is neither risk capital nor a budget line. None of these four totals is a national census; each is what this project has gathered and sourced so far. For the strategy discussion, the pattern across the five comparable projects matters more than the totals. Two (Dresden, Grünheide) show large, resource-intensive projects moving from announcement to construction or a workable compromise within one to two years, despite real environmental concerns. Two (Magdeburg, Heide) show that political and financial backing, even subsidies in the billions, does not guarantee that a project survives its own execution risk. SuedLink shows that sustained opposition across several states can force a fundamental redesign without stopping a project outright. None of the six data-centre cases on this map has yet reached a resolution by redesign like Grünheide's or SuedLink's; that is worth watching as the cases develop.

Sources for the funding chart. Stadt Groß-Gerau (2026-02, primary) and Vantage Data Centers' own stated figure, via the city's release, for Groß-Gerau. Developer FAB's own figure, via datacenter-insider.de and Eisenach Online, for Eisenach. EdgeConneX's own figure, via hessenschau.de, for Maintal. Land NRW (2026) for the RWTH Aachen AI-Center. FZ Jülich; Eviden; ParTec (2026) for JUPITER's €500m system-and-operations cost and its EU/BMBF/NRW split. GWK (2026) for the NHR-Verbund AI-capacity tranche. Fraunhofer IZB (2026) for NG-HPDAC. Helmholtz and MPG (2026) for DKRZ. KIT (2026) for its own AI data centre. None of these figures has been triangulated beyond what each entity or its funders state. Treat this as a first pass at the funding, not a verified census.

Sources for Map 3. Microsoft (2026-07-01) press release; Stadt Grevenbroich (2026); Handelsblatt (2026, three articles); Land NRW / wirtschaft.nrw (2026): Grevenbroich. Stadt Eisenach (2026); Eisenach Online (2025, 2026); datacenter-insider.de (2026); Rhönkanal (2026): Eisenach. Gewerbesteuer-Infoportal (2026); LWL-Statistik; sevdesk (2026); Bund der Steuerzahler NRW/RLP (2017): Monheim am Rhein. hessenschau.de (2026-02-04): Groß-Gerau. ZDFheute (2026); Solarserver (2026): Maintal. Solarserver (2026); klimareporter.de (2026): Birstein. Each entry was checked against a verbatim capture of its sources on 30 September 2026. Figures beyond what each entry states have not been triangulated.

Sources for the comparable-projects layer, added 9 September 2026. wiwo.de; electrive.net; European Commission state-aid approval; t-online.de/dresden; tech-insider.org; Land Sachsen: Dresden/ESMC. ZDF; ZDFheute; WSWS.org; Junge Freiheit; notebookcheck.com: Magdeburg/Intel. wiwo.de; t-online.de; taz.de; freitag.de; mobilitree.net; elektroauto-news.net: Grünheide/Tesla. ZDF; ZDFheute; transport-online.de; ecomento.de (state audit court finding): Heide/Northvolt. Stuttgarter Zeitung; ZfK; Deutscher Bundestag Wissenschaftliche Dienste WD 5-3000-136/24; energie-chronik.de; diebayern.de: SuedLink. As with the rest of Map 3, each entry was checked against a verbatim capture on 30 September 2026, and nothing beyond what it states has been triangulated. The SuedLink marker in particular sits at one documented flashpoint on a 700 km corridor, not at a precise site.

International context. All three maps cover Germany only. Globally, the US leads by build-out scale (about 80% of world capacity under construction in 2025; about 25 GW under construction and about 191 GW planned in the Americas; Cushman & Wakefield, 2026). The Middle East leads by growth rate (from about 1 GW to about 3.3 GW by 2030), with far fewer consent fights than the Eisenach and Grevenbroich cases here, because sovereign backing largely removes local opposition (PwC/Computer Weekly, 2025 to 2026). Full comparison: our overview of global geographies.