As of 30 September 2026
How fast data centres get built depends on the connection capacity available at a specific point on a specific network, by a specific date. This map shows where that limit runs: what is in operation, what is planned and where a site could still realistically be secured.
Germany only · Evidence tier and confidence stated for each site · Every marker says whether it is on record or our inference
How to read the counts. The built layer shows city clusters rather than individual buildings: one circle per market. A circle is sized by published IT capacity in megawatts where a figure exists, and drawn as a small fixed mark where none does. Sources disagree on the national total, and we have not averaged them. Cloudscene counts 529 data centres in Germany; a colocation-portfolio database counts 194 existing and 43 upcoming; trade coverage says roughly 500. The gap comes from scope: every facility including small hosting, against colocation only. Live IT load is shown where a figure is published, which is Frankfurt, Munich and Berlin.
How to read the dots. The dots are not our projects. They mark positions in the market, graded by how settled the information is. Built and planned come from the evidence base and carry its tier. Potential is our own inference from ownership and existing grid connections. It is deliberately the thinnest layer on the map: nobody publishes this information, and it can be gathered only in conversations on the ground, never at a desk.
We name these gaps explicitly, because the next piece of work lies in them.
Since 1 April 2026 the four transmission system operators have allocated extra-high-voltage connection capacity through the maturity procedure (Reifegradverfahren) instead of first come, first served. Applications are collected in fixed rounds per control zone and ranked together. A site therefore competes for a switching bay with the other applicants in its own zone. A site 30 kilometres away, across a zone boundary, is in a different contest. That is why Nierstein and Hanau are neighbours only on the map.
The zone shading is approximate. Each Land is coloured by its predominant transmission operator. The real control-zone boundaries do not follow Land borders, and Hesse, Bavaria and North Rhine-Westphalia are split in ways this shading does not show.
A site below the transmission level can still be caught by the procedure. Added 9 September 2026. The maturity procedure covers connections to the transmission grid, the extra-high-voltage level of 220 and 380 kV. A load of roughly 5 to 10 MW and more connects at 110 kV, which in Germany is the high-voltage level of the distribution grid; a load of roughly 100 MW connects at 380 kV. A site of 20 to 50 MW therefore sits at distribution level and looks exempt. It usually is not: TransnetBW's own procedure page lists ad-hoc requests from distribution operators to the transmission grid as covered too. Where the local distribution operator has no headroom, it must apply upstream. The site then sits in the queue as one line in someone else's application, without the levers (secured land, permits, equipment orders) that directly improve a ranking in the procedure. Several planned sites on this map, among them Colt DCS at 54 MW and Data Center Partners' Munich site at 17 MW, fall exactly into this size band.
Our driver model weighs the five factors that do most to decide where a data centre goes in Germany. Four of the five are now asked for explicitly in a connection application under the maturity procedure. Each driver has its own toggle above the map, off by default. Switching one on shades the areas the model rates for that driver: solid fill where the evidence rates it favourable, a dashed outline with light fill where it is constrained, and hatching where it is unfavourable or absent. Click a shaded area for its rating, the statement it rests on and the source.
What this layer is not. These are the three or four areas the
driver model actually analysed, drawn as ellipses that approximate their extent. They are not a national
survey. A blank area under any of the five toggles means the model has not assessed it, and says
nothing about the driver there. The ratings are this project's own synthesis
(labelled [inference] in the source document) and rest on evidence of only
medium confidence. Berlin's growth rate comes from a trade source not checked against a primary. The
Berlin allocation figure comes from the operator's own results as reported by ZfK (May 2026), and the
Nauen status was checked against independent sources on 21 September 2026.
Sorted by status, then size. Nothing here is verified beyond the tier stated.
| Position | Status | Scale | Party | Control zone | Source, tier, confidence |
|---|---|---|---|---|---|
| Frankfurt / Rhine-Main Hesse |
built | 131 facilities 997 MW |
131 facilities listed on Cloudscene. Equinix, Digital Realty (24 data centres in the metro, per its own page), NTT, CyrusOne, Vantage, CloudHQ (Offenbach campus, 112 MW critical IT load), Telehouse, NorthC and others | TenneT | JLL (2026-04-17; mid-year 2026); Bitkom (2026-03); Mainova via t3n (2026-03-18); TenneT (n.d., MainNetzausbau); Mainova (n.d.); Amprion (2021); Cloudscene (2026); Digital Realty (n.d.); CloudHQ (n.d.) Tier 1-2 (grid operators, city utility) for the connection constraint; Tier 3-4 (Bitkom, JLL, Cloudscene) for capacity and counts · High on the connection constraint and the order of magnitude; medium on exact MW, which differ by definition between JLL (colocation and hyperscale) and Bitkom (all data centres) · checked 2026-09-30 |
| Munich Bavaria |
built | 55 facilities 102 MW |
55 facilities listed on Cloudscene. NorthC (two sites: Balanstrasse, 2 MW; Wamslerstraße, 1.17 MW, taken over from Colt on 1 September 2025), Equinix and others | TenneT | Cloudscene (2026); JLL (2026-04-17); NorthC (n.d.; 2025); Data Center Knowledge (2026-03-18) Tier 4 (directory, broker) + Tier 5 (operator) · Medium · checked 2026-09-30 |
| Hamburg Hamburg |
built | 53 facilities | 53 facilities listed on Cloudscene. NorthC (Süderstraße 198: 1.17 MW today, 4.1 MW installed electrical power listed as a future upgrade), NTT and others | 50Hertz | Cloudscene (2026); NorthC (n.d.; 2025); Data Center Knowledge (2026-03-18) Tier 4 (directory) + Tier 5 (operator) · Medium · checked 2026-09-30 |
| Berlin Berlin |
built | 45 facilities 136 MW |
45 facilities listed on Cloudscene. NorthC (Gradestraße 60, taken over from Colt on 1 September 2025), Google cloud region and others | 50Hertz | ZfK (2026-05-04); JLL (2026-04-17); Cloudscene (2026); NorthC (n.d.) Tier 3 to 4 · Medium to high · checked 2026-09-30 |
| Düsseldorf North Rhine-Westphalia |
built | 38 facilities | 38 facilities listed on Cloudscene. Digital Realty (three data centres on In der Steele, 16,750 m² colocation space in total), Equinix, NorthC (In der Steele 37A, taken over from Colt on 1 September 2025), NMMN (sells colocation in a facility it describes as over 10,000 m² and 20 MW), aixit | Amprion | Cloudscene (2026); JLL (2026-04-17); Digital Realty (n.d.); NorthC (n.d.); NMMN (n.d.) Tier 4 to 5 · Medium · checked 2026-09-30 |
| Nuremberg Bavaria |
built | 27 facilities | 27 facilities listed on Cloudscene. NorthC (Am Tower 5), noris network and others | TenneT | Cloudscene (2026); NorthC (n.d.) Tier 4 · Medium · checked 2026-09-30 |
| Stuttgart Baden-Württemberg |
built | 25 facilities | 25 facilities listed on Cloudscene. NMMN (three sites: Gropiusplatz, Schickardstraße, Neue Brücke), nexspace (new Sternhöhe site, opening given as 09/2026 on its English page and Q4 2026 on its German page) | TransnetBW | Cloudscene (2026); NMMN (n.d.); nexspace (n.d.) Tier 4 to 5 · Low to medium · checked 2026-09-30 |
| Cologne North Rhine-Westphalia |
built | 15 facilities | 15 facilities | Amprion | Cloudscene (2026) Tier 4 · Low to medium · checked 2026-09-30 |
| Dortmund North Rhine-Westphalia |
built | 9 facilities | 9 facilities | Amprion | Cloudscene (2026) Tier 4 · Low · checked 2026-09-30 |
| Hanover Lower Saxony |
built | 9 facilities | 9 facilities | TenneT | Cloudscene (2026) Tier 4 · Low · checked 2026-09-30 |
| Bremen Bremen |
built | 8 facilities | 8 facilities listed on Cloudscene, including ColocationIX | TenneT | Cloudscene (2026) Tier 4 · Low · checked 2026-09-30 |
| Leipzig Saxony |
built | 7 facilities | 7 facilities | 50Hertz | Cloudscene (2026) Tier 4 · Low · checked 2026-09-30 |
| Karlsruhe Baden-Württemberg |
built | 7 facilities | 7 facilities | TransnetBW | Cloudscene (2026) Tier 4 · Low · checked 2026-09-30 |
| Dresden Saxony |
built | 5 facilities | 5 facilities | 50Hertz | Cloudscene (2026) Tier 4 · Low · checked 2026-09-30 |
| Kiel Schleswig-Holstein |
built | 3 facilities | 3 facilities | TenneT | Cloudscene (2026) Tier 4 · Low · checked 2026-09-30 |
| Bielefeld North Rhine-Westphalia |
built | 2 facilities | 2 facilities | TenneT | Cloudscene (2026) Tier 4 · Low · checked 2026-09-30 |
| Hanau (Google) Hesse |
built | not published | TenneT | Stadt Hanau (2026-04-28); Hessische Landesregierung (2026-04-28); Google (n.d.); Data Center Knowledge (2026-03-18) Tier 2 (city, state) + Tier 5 (operator) · High · checked 2026-09-30 | |
| Nierstein Rhineland-Palatinate |
planned | 482 MW | NTT Global Data Centers | Amprion | heise online / dpa (2026-01/02), citing NTT Tier 3 (independent press, company statement) · High on operator, size and zoning; medium on timing · checked 2026-09-30 |
| Dummerstorf (Schwarz Digits) Mecklenburg-Vorpommern |
planned | 240 MW | Schwarz Digits | 50Hertz | Schwarz Gruppe press release (2026-08-27); ZDFheute / dpa (2026-08-27); heise online (2026-08-27) Primary (company) + Tier 3 · High on the announcement; low on timing, which is permit-dependent · checked 2026-09-30 |
| Wustermark (Virtus) Brandenburg |
planned | 204 MW | Virtus (ST Telemedia) | 50Hertz | Virtus Wustermark campus page (accessed 2026-09-30); STT GDC / Virtus newsroom (2023-09-04) Primary (company) · High on the company's current figures; timing has slipped once · checked 2026-09-30 |
| Lübbenau (Schwarz Digits) Brandenburg |
planned | 200 MW | Schwarz Digits | 50Hertz | Schwarz Digits release (2025-11-17, via Silicon Saxony reprint) and Datacenter Lübbenau page; Stadt Lübbenau/Spreewald (2025-11) Primary (company) + Tier 2 (municipality) · High · checked 2026-09-30 |
| East of Berlin (Colt DCS) Brandenburg |
planned | 54 MW | Colt DCS | 50Hertz | Colt DCS press release (2025-04) and Berlin 1 and 2 location page; CIO.de / dpa (2025-07) Primary (company) + Tier 3 · High on the plan; medium on timing · checked 2026-09-30 |
| Munich (Data Center Partners) Bavaria (Unterschleißheim, north of Munich) |
planned | 17 MW | Data Center Partners | TenneT | DatacenterDynamics (2025); CMS Hasche Sigle on the EnEfG cabinet draft (2026) Tier 3 · Medium: single trade source for the project · checked 2026-09-30 |
| Bergheim (Microsoft) North Rhine-Westphalia |
planned | not published | Microsoft | Amprion | Land NRW (2026-03-12); Microsoft (2026-03-12; 2024-02-15) Tier 2 (state) + Tier 3 · High on the event, medium on the €3.2bn split · checked 2026-09-30 |
| Bedburg (Microsoft) North Rhine-Westphalia |
planned | not published | Microsoft | Amprion | Microsoft (2026-03-12) press release; heise online (2026-07-01) Primary (company) + Tier 3 · High on permit and status; MW unknown · checked 2026-09-30 |
| Elsdorf (Microsoft) North Rhine-Westphalia |
planned | not published | Microsoft | Amprion | Microsoft (2026-03-12) press release; heise online (2026-07-01) Primary (company) + Tier 3 · Medium: permit status dated July 2026 · checked 2026-09-30 |
| Dietzenbach (Google) Hesse |
planned | not published | TenneT | Google Cloud press release (2025-11-11); Kreisstadt Dietzenbach (2025-11) Primary (company) + Tier 2 (municipality) · High on the announcement and the heat deal; MW not published · checked 2026-09-30 | |
| AWS European Sovereign Cloud Brandenburg (exact site not published) |
planned | not published | AWS | 50Hertz | AWS press releases: press.aboutamazon.com (2026-01-15), aboutamazon.eu (2024-05-15), aboutamazon.de (2024-06-19) Primary (company) · High on the commitments; low on the exact site · checked 2026-09-30 |
| Nauen (maincubes) Brandenburg |
planned | not published | maincubes | 50Hertz | maincubes website and press releases (2024 to 2026, captured 2026-09-25); Stadt Nauen; connect-professional; datacenter-insider.de Tier 5 company primary, corroborated by the municipality and two trade outlets · High on status; medium on dates, which the company states inconsistently · checked 2026-09-30 |
| Großkrotzenburg (Uniper) Hesse |
planned | not published | Uniper | TenneT | Uniper / TenneT joint release (2026-01-22, via MarketScreener reprint); IZ Immobilien Zeitung (2026-07); ms-aktuell (2026-09-06) Primary (via reprint) + Tier 3 · High on the transaction; medium on the data-centre area · checked 2026-09-30 |
| Grevenbroich (Microsoft) North Rhine-Westphalia |
planned | not published | Microsoft | Amprion | Microsoft (2026-07-01) press release; Stadt Grevenbroich news and project page (2026-07); heise online (2026-07-01); Handelsblatt (2026); datacenter-insider.de (2026-07); Landtag NRW petition committee (2025-01-14) Primary (company) + Tier 2 (city) + Tier 3 · High on the announcement and site; low on investment size; medium on consent · checked 2026-09-30 |
| Eisenach (developer FAB, project stalled) Thuringia |
planned | not published | FAB, Leipzig (developer; end investor not yet named) | 50Hertz | Eisenach Online (July 2026, report of the council session of 1 July); Stadt Eisenach, Blue Future project page; Rhönkanal (2026-03) Tier 2 (city) + Tier 3 · High on the vote, date and outcome; medium on the pre-vote plan figures · checked 2026-09-30 |
| Frimmersdorf (RWE land) North Rhine-Westphalia |
planned | not published | RWE (site owner) | Amprion | Stadt Grevenbroich (plan presentation with NRW, Rhein-Kreis Neuss and RWE); NRW.URBAN project page (accessed 2026-09-30); Stadt Grevenbroich Microsoft Q&A (2026-07) Tier 2 (city, state development company) · Medium to high on the plan; timing depends on the investor tender · checked 2026-09-30 |
| Weisweiler (RWE land) North Rhine-Westphalia |
potential | not published | RWE (site owner) | Amprion | RWE 'energised Land' page (accessed 2026-09-30); Reuters (2026-08-13); KVBG Anlage 2 Tier 5 + Tier 1 (statute) + inference · Low · checked 2026-09-30 |
| Neurath (RWE land) North Rhine-Westphalia |
potential | not published | RWE (site owner) | Amprion | KVBG Anlage 2; Stadt Grevenbroich project page (2026-07); RWE 'energised Land' page Tier 1 (statute) + Tier 2 (city) + Tier 5 + inference · Low · checked 2026-09-30 |
| Hürth (RWE land) North Rhine-Westphalia |
potential | not published | RWE (site owner) | Amprion | RWE Knapsacker Hügel site page (accessed 2026-09-30); RWE 'energised Land' page Tier 5 + inference · Low · checked 2026-09-30 |
| Niederaussem (RWE) North Rhine-Westphalia |
potential | not published | RWE | Amprion | RWE AG press release (2011-09-23, via firmenpresse); CIO.de (c. 2016-17); KVBG Anlage 2 Primary (company, 2011) + Tier 3 + Tier 1 (statute) · High on the history; low on any future use · checked 2026-09-30 |
AWS. (2026, January 15). AWS launches AWS European Sovereign Cloud and announces expansion across Europe [Press release]. Primary.
CBRE. (2025). Frankfurt becomes a 1GW data centre market; 2025 Global Data Center Investor Intentions Survey.
Cloudscene. (2026). Germany data center market overview. Directory; self-reported, tier 4.
Digital Realty. (n.d.). EMEA data centers. Company site; primary for its own facilities.
Google. (2026). 5,5 Milliarden Euro für Deutschlands digitale Zukunft; hessenschau (2026); Hessen state government. Dietzenbach and Hanau.
Land Nordrhein-Westfalen. (2026, March 12). Spatenstich für die Microsoft Rechenzentren im Rheinischen Revier. State government; tier 2. With Microsoft (2026) and Handelsblatt (2026) for the €3.2bn figure.
NorthC. (n.d.). Data centre locations. Company site; primary for its own facilities.
Data Center Dynamics. (2026). German utility RWE completes Niederaussem data center.
Data Center Knowledge. (2026). Germany's data center market expands amid power and regulatory pressures.
RWE. (n.d.). "energised Land" — Energy for data centres. Company marketing page; tier 5 and interested on every figure.
TechPolicy.Press. (2025). Germany's data center boom is pushing the power grid to its limits.
Übertragungsnetzbetreiber (50Hertz, Amprion, TenneT Germany, TransnetBW). (2026, February 5). Reifegradverfahren für Netzanschlüsse an das Übertragungsnetz (V1.00), and the joint press release of the same date. Primary.
Uniper & TenneT Germany. (2026, January 22). Reaching the goal faster together. Primary, read in a reprint.
Internal: our Germany profile and risk register; our research on customers, demand and hurdles; and our siting model (the five siting-driver layers).
Map 2 · exploratory · outside the evidence base
Map 1 shows only what this project has evidence for. This second map works the other way round. Using the same five drivers, it asks where in Germany the conditions that made the Rhenish belt attractive for data centres might also exist, in areas where, as far as our research has found, no developer, utility or hyperscaler has moved in yet. Every rating here is our own reasoning from public knowledge of Germany's coal exit and grid build-out, done at Moritz's request. None of it has been checked against a primary source, and none of it carries a project citation as Map 1 does. Read it as a list of places worth a site visit, not as a finding.
Speculative · 7 and 8 September 2026 · same five drivers and colours as Map 1 · every rating tiered "Speculative, unverified" or "Project-sourced" (stated per entry) · confidence mostly low
Why these five areas. Two are Germany's other two federally designated lignite regions (the Rhenish belt, already on Map 1, is the third): Lusatia, where LEAG plays the role RWE plays in the Rhenish belt, and the Mitteldeutsches Revier south of Leipzig, where MIBRAG does. The third, the wider Ruhr, extends the logic of existing power-plant connections to the hard-coal and gas fleet beyond the Rhenish core, in the same crowded Amprion zone as the committed Microsoft cluster. The fourth, the Schleswig-Holstein wind corridor, works by a different mechanism: new transmission capacity is being built there, SuedLink to carry wind power south and NordLink to link with Norway, and no industrial connection is inherited. The fifth, added 8 September 2026, is different again: Rhein-Neckar & Neckarsulm was chosen for its customers, because two named, well-funded buyers (SAP, Schwarz Digits) already sit there, according to our demand research. The "Potential customers" layer below shows that link. The faint grey dots are Map 1's built and planned positions, shown for orientation only; they are not part of this layer.
Sources for Map 2 (general knowledge, not project research): Bundesministerium für Wirtschaft und Klimaschutz / Strukturstärkungsgesetz Kohleregionen (2020), for the three designated German lignite regions and their structural funding. LEAG, public statements on converting former mining and plant sites ("GigawattFactory"). TenneT / 50Hertz / Amprion, public project information on the SuedLink and NordLink corridors; their roles were checked against TenneT's SuedLink page on 30 September 2026. Schleswig-Holstein state government, public statements of its hydrogen and power-to-X strategy. Apart from that one check, none of these has been compared with a primary source. Every figure and claim above needs verification before it is used for anything beyond choosing where to look next.
Map 3 · political and municipal investment climate
Driver 3 on Map 1 rates consent and local politics by region. This map asks the same question where it is actually decided: one council, one mayor, one vote. Every marker below is a named, dated event or decision. That includes the unfavourable ones, which we found by deliberately searching for opposition, as our research standard requires: it tells us to look actively for evidence against our own view.
6 markers · every entry sourced and tiered individually
How to read this map. A favourable marker is active support from an elected mayor or council. For Monheim am Rhein it marks a fiscal-policy benchmark of how far investment-friendliness goes nationally; the town has no known data-centre interest and is on the map for comparison only. An unfavourable marker is a recorded council vote against, or an operator halting work after protest. Contested sits between the two: a citizen initiative and an elected council at odds, with the outcome still open.
Added 9 September 2026. The chart shows every disclosed funding figure for the six sites on this map, together with the German academic and research-computing funding gathered in the same session (our demand research, segment 8), summed and compared. Only stated, disclosed figures are charted. Nobody involved has disclosed the investment for Grevenbroich or Birstein. Trade press floats ranges, but turning a range into a point estimate would present a guess as a fact, so both are left out here and marked undisclosed in their own panels.
Totals: all 14 disclosed figures on this page, €37,238m combined. Private commercial: €5,600m across four projects (the three Map 3 data-centre cases plus the Grünheide expansion). Three of the four, Groß-Gerau, Eisenach and Maintal, are now rejected, paused or stopped, so this is capital proposed rather than deployed. Public: €11,637.7m across eight items: six academic and research programmes (segment 8) plus two subsidy pledges to private projects that have since failed (Magdeburg, Heide). That deserves attention: most of the disclosed "public" figure on this page is subsidy committed to industry rather than spending on public research infrastructure. Mixed: €10,000m, one project (Dresden/ESMC), roughly half private capital and half federal subsidy in the same fab. Regulated: €10,000m, one project (SuedLink), paid for by the grid operators and recovered from every electricity consumer through network charges; it is neither risk capital nor a budget line. None of these four totals is a national census; each is what this project has gathered and sourced so far. For the strategy discussion, the pattern across the five comparable projects matters more than the totals. Two (Dresden, Grünheide) show large, resource-intensive projects moving from announcement to construction or a workable compromise within one to two years, despite real environmental concerns. Two (Magdeburg, Heide) show that political and financial backing, even subsidies in the billions, does not guarantee that a project survives its own execution risk. SuedLink shows that sustained opposition across several states can force a fundamental redesign without stopping a project outright. None of the six data-centre cases on this map has yet reached a resolution by redesign like Grünheide's or SuedLink's; that is worth watching as the cases develop.
Sources for the funding chart. Stadt Groß-Gerau (2026-02, primary) and Vantage Data Centers' own stated figure, via the city's release, for Groß-Gerau. Developer FAB's own figure, via datacenter-insider.de and Eisenach Online, for Eisenach. EdgeConneX's own figure, via hessenschau.de, for Maintal. Land NRW (2026) for the RWTH Aachen AI-Center. FZ Jülich; Eviden; ParTec (2026) for JUPITER's €500m system-and-operations cost and its EU/BMBF/NRW split. GWK (2026) for the NHR-Verbund AI-capacity tranche. Fraunhofer IZB (2026) for NG-HPDAC. Helmholtz and MPG (2026) for DKRZ. KIT (2026) for its own AI data centre. None of these figures has been triangulated beyond what each entity or its funders state. Treat this as a first pass at the funding, not a verified census.
Sources for Map 3. Microsoft (2026-07-01) press release; Stadt Grevenbroich (2026); Handelsblatt (2026, three articles); Land NRW / wirtschaft.nrw (2026): Grevenbroich. Stadt Eisenach (2026); Eisenach Online (2025, 2026); datacenter-insider.de (2026); Rhönkanal (2026): Eisenach. Gewerbesteuer-Infoportal (2026); LWL-Statistik; sevdesk (2026); Bund der Steuerzahler NRW/RLP (2017): Monheim am Rhein. hessenschau.de (2026-02-04): Groß-Gerau. ZDFheute (2026); Solarserver (2026): Maintal. Solarserver (2026); klimareporter.de (2026): Birstein. Each entry was checked against a verbatim capture of its sources on 30 September 2026. Figures beyond what each entry states have not been triangulated.
Sources for the comparable-projects layer, added 9 September 2026. wiwo.de; electrive.net; European Commission state-aid approval; t-online.de/dresden; tech-insider.org; Land Sachsen: Dresden/ESMC. ZDF; ZDFheute; WSWS.org; Junge Freiheit; notebookcheck.com: Magdeburg/Intel. wiwo.de; t-online.de; taz.de; freitag.de; mobilitree.net; elektroauto-news.net: Grünheide/Tesla. ZDF; ZDFheute; transport-online.de; ecomento.de (state audit court finding): Heide/Northvolt. Stuttgarter Zeitung; ZfK; Deutscher Bundestag Wissenschaftliche Dienste WD 5-3000-136/24; energie-chronik.de; diebayern.de: SuedLink. As with the rest of Map 3, each entry was checked against a verbatim capture on 30 September 2026, and nothing beyond what it states has been triangulated. The SuedLink marker in particular sits at one documented flashpoint on a 700 km corridor, not at a precise site.
International context. All three maps cover Germany only. Globally, the US leads by build-out scale (about 80% of world capacity under construction in 2025; about 25 GW under construction and about 191 GW planned in the Americas; Cushman & Wakefield, 2026). The Middle East leads by growth rate (from about 1 GW to about 3.3 GW by 2030), with far fewer consent fights than the Eisenach and Grevenbroich cases here, because sovereign backing largely removes local opposition (PwC/Computer Weekly, 2025 to 2026). Full comparison: our overview of global geographies.